目 录
目 录 ................................................................... 1 施工方案调整变更索引表 .................................................... 3 第一章 工程概况 ........................................................... 4 1.1工程概况: ............................................................ 4 1.2编制依据: ............................................................ 4 1.3现场条件: ............................................................ 4 第二章 施工部署 ........................................................... 4 2.1施工顺序: ............................................................ 4 2.2承包方式: ............................................................ 4 2.3料场安排: ............................................................ 4 第三章 施工准备 ........................................................... 5 3.1技术准备: ............................................................ 5 3.2材料、设备准备: ...................................................... 5 3.3人员准备: ............................................................ 6 3.4设备准备: ............................................................ 6 3.5其他准备工作: ........................................................ 6 第四章 施工方法 ........................................................... 7 3.1 普通木门、窗安装: .................................................... 7 3.1.1施工顺序: ........................................................ 7 3.1.2 木门框安装: ...................................................... 7 3.1.4 门扇安装: ........................................................ 7 3.1.5 木门小五金安装: .................................................. 7 4.2铝合金门窗安装: ...................................................... 7 4.3防火门安装: .......................................................... 8 4.3.1木制防火门安装: .................................................. 8 4.3.2钢制防火门安装: .................................................. 8
4.4人防门安装: .......................................................... 9 4.4.1施工顺序: ........................................................ 9 4.4.2人防门安装: ...................................................... 9 4.6复合防火卷帘门安装: .................................................. 9 4.6.1 构成: ............................................................ 9 4.6.2 安装步骤及调试: .................................................. 9 4.6.3 操作维护与保养 ................................................... 10 第五章 技术质量保证措施 .................................................. 10 5.1木门、木制防火门: ................................................... 10 5.1.1门窗质量: ....................................................... 10 5.1.2安装质量: ....................................................... 11 5.2铝合金门窗: ......................................................... 11 5.3钢制防火门: ......................................................... 12 5.3.1材料与配件: ..................................................... 12 5.3.2外观质量: ....................................................... 12 5.3.3安装质量: ....................................................... 13 5.4防火卷帘门: ......................................................... 13 5.4.1卷帘质量要求 ..................................................... 13 5.4.2安装质量: ....................................................... 13 第六章 安全技术措施 ...................................................... 14 第七章 成品保护措施 ...................................................... 15
施工方案调整变更索引表
第一章 工程概况
1.1工程概况:
本工程所使用的主要有:普通木门、钢制防火门、钢制隔音防火门、木制防火门、铝合金门窗、铝合金百叶窗、防火卷帘门。
具体门窗的洞口尺寸规格数量详见附表1。 1.2编制依据:
1、清华科技园创新中心工程建筑施工蓝图; 2、《建筑构造通用图籍88JX5-1》;
3、北京市通用图集《常用木门、钢木门》京95-J61;
4、中华人民共和国国家标准《钢质防火门通用技术条件》(GB12955-91); 1.3现场条件: 1、现场条件:
外墙砌筑已经完成,外墙石材基本正在进行中,多数外墙脚手架采用单排脚手架,且暂时不能拆除,其连墙杆影响外窗安装;现场建有砂浆搅拌站。 2、材料供应:
所有门窗均由甲方定货。进场的门窗按项目物资管理的要求,暂定堆放于首层,用多层板维护的专用库房内;
第二章 施工部署
2.1施工顺序:
内、外门窗框及扇安装跟随抹灰工程顺序进行,内门窗安装由下向上,外门窗框安装由上向下;外窗扇安装分两步自上而下进行,其中部分受脚手架影响外窗的安装随外架拆除穿插进行。 2.2承包方式:
总包:中建一局集团公司清华科技园创新中心工程项目经理部 分包:防火卷帘安装、铝合金门窗安装由业主直接分包 2.3料场安排:
门窗进场后堆放在楼内划分的区域内,并增加围挡。
第三章 施工准备
3.1技术准备: 3.1.1审图:
正式进入门窗安装施工前,认真查阅图纸、洽商、方案和相关规范,确定各类门窗数量及安装部位,核对结构工程预留位臵大小的准确性,找出抹灰施工中的关键点和难点以及施工工序交叉问题,并提出处理办法。 3.1.2管理人员及劳务人员培训、教育: